Evaluating Risk

Here, I am going to re-cap on some pre-existing risk management theory in order to set the scene for the next section which heads back to looking at risk on software projects.

Risk Registers

Most developers are familiar with recording issues in an issue tracker. For all of the same reasons, it’s good practice to record the risks you face running a project or an operation in a Risk Register. Typically, this will include for each risk:

  • The name of the risk, or other identifier.
  • A categories to which the risk belongs (this is the focus of the Risk Landscape section in Part 2).
  • A brief description or name of the risk to make the risk easy to discuss.
  • Some estimate for the Impact, Probability or Risk Score of the risk.
  • Proposed actions and a log of the progress made to manage the risk.

Some points about this description:

A Continuum of Formality

Remember back to the Dinner Party example at the start: the Risk Register happened entirely in your head. There is a continuum all the way from “in your head” through “using a spreadsheet” to dedicated Risk Management software.

It’s also going to be useful in conversation, and this is where the value of the Risk-First approach is: providing a vocabulary to talk about risks with your team.

Probability And Impact

Probability is how likely something is to happen, whilst Impact is the cost (usually financial) when it does happen.

In a financial context (or a gambling one), we can consider the overall Risk Score as being the sum of the Impact of each outcome multiplied by its Probability. For example, if you buy a 1-Euro ticket in a raffle, there are two outcomes: win or lose. The impact of winning would be (say) a hundred Euros, but the probability might be 1 in 200. The impact of losing would be the loss of 1 Euro, with

Outcome Impact Probabilty Risk Score
Win + 99 EUR 1 in 200 .5 EUR
Lose - 1 EUR 199 in 200 -.99 EUR

Risk Management in the finance industry starts here and gets more complex. But often (especially on a software project), it’s better to skip all this, and just figure out a Risk Score. This is because if you think about “impact”, it implies a definite, discrete event occurring (or not occurring) and asks you then to consider the probability of that.

Risk-First takes a view that risks are a continuous quantity, more like money or water: by taking an action before delivering a project you might add a degree of Schedule Risk, but decrease the Operational Risk later on by a greater amount.

Risk Matrix

Risk Register of Dinner Party Risks

A risk matrix presents a graphical view on where risks exist. The diagram above is an example, showing the risks from the dinner party in the A Simple Scenario section:

This type of graphic is helpful in deciding what to do next, although alternatively, you can graph the overall Risk Score against the Payoff. Easily mitigated risk (on the right), and worse risks (at the top) can therefore be dealt with first (hopefully).

Risk Register of Dinner Party Risks, Considering Payoff

Unknown Unknowns

One of the criticisms of the Risk Register approach is that of mistaking the map for the territory. That is, mistakenly believing that what’s on the Risk Register is all there is.

In the preceding discussions, I have been careful to point out the existence of Hidden Risks for that very reason. Or, to put another way:

“What we don’t know is what usually gets us killed” - Petyr Baelish, Game of Thrones

Donald Rumsfeld’s famous Known Knowns is also a helpful conceptualisation:

  • A known unknown is an Attendant Risk. i.e. something you are aware of, but where the precise degree of threat can’t be established.
  • An unknown unknown is a Hidden Risk. i.e a risk you haven’t even thought to exist yet.

Risk And Uncertainty

Arguably, Risk-First uses the term ‘Risk’ wrongly: most literature suggests risk can be measured whereas uncertainty represents things that cannot.

I am using risk everywhere because later we will talk about specific risks (e.g. Boundary Risk or Complexity Risk), and it doesn’t feel grammatically correct to talk about those as uncertainties, especially given the pre-existing usage in Banking of terms like Operational Risk or Reputational risk which are also not really a-priori measurable.

The Opposite Of Risk Management

Let’s look at a classic description of Risk Management:

“Risk Management is the process of thinking out corrective actions before a problem occurs, while it’s still an abstraction. The opposite of risk management is crisis management, trying to figure out what to do about the problem after it happens.” - Waltzing With Bears, De Marco, Lister

This is not how Risk-First sees it:

First, we have the notion that Risks are discrete events. Some risks are (like gambling on a horse race), but most aren’t. In the Dinner Party, for example, bad preparation is going to mean a worse time for everyone, but how good a time you’re having is a spectrum, it doesn’t divide neatly into just “good” or “bad”.

Second, the opposite of “Risk Management” (or trying to minimise the “Down-side”) is either “Upside Risk Management”, (trying to maximise the good things happening), or it’s trying to make as many bad things happen as possible.

Third, Crisis Management is still just Risk Management: the crisis (Earthquake, whatever) has happened. You can’t manage it because it’s in the past. All you can do is Risk Manage the future (minimize further casualties and human suffering, for example).

Yes, it’s fine to say “we’re in crisis”, but to assume there is a different strategy for dealing with it is a mistake: this is the Fallacy of Sunk Costs.

Invariances #1: Panic Invariance

You would expect that any methods for managing software delivery should be invariant to the degree of crisis in the project. If, for example, a project proceeds using Scrum for eight months, and then the deadline looms and everyone agrees to throw Scrum out of the window and start hacking, then this implies there is a problem with Scrum, and that it is not Panic Invariant. In fact, many tools like Scrum don’t consider this:

  • If there is a production outage during the working week, we don’t wait for the next Scrum Sprint to fix it.
  • Although a 40-hour work-week is a great idea, this goes out of the window if the databases all crash on a Saturday morning.

In these cases, we (hopefully calmly) evaluate the risks and Take Action.

This is Panic Invariance: your methodology shouldn’t need to change given the amount of pressure or importance on the table.

Invariances #2: Scale Invariance

We are used to the idea that physical laws work at any scale: if they don’t apply equally to big and small scenarios then that implies something is wrong. For example, Newton’s Laws of Motion work fine for artillery shells but fail to calculate the orbital period of Mercury, which led to Einstein trying to improve on them with the Theory of Relativity.

Ideally, a methodology should be applicable at any scale too:

  • A single class or function.
  • A collection of functions, or a library.
  • A project team.
  • A department.
  • An entire organisation.

In practice, however, we usually find methodologies are tuned for certain scales. For example, Extreme Programming is designed for small, co-located teams. And, that’s useful. But the fact it doesn’t scale tells us something about it: chiefly, that it considers certain kinds of risk, while ignoring others. At small scales that works ok, but at larger scales other risks (such as team Coordination Risk) increase too fast for it to work.

If the methodology fails at a particular scale this tells you something about the risks that the methodology isn’t addressing. One of the things Risk-First explores is trying to place methodologies and practices within a framework to say when they are applicable.

Value vs Speed

“Upside Risk”

“Upside Risk” isn’t a commonly used term: industry tends to prefer “value”, as in “Is this a value-add project?”. There is plenty of theory surrounding Value, such as Porter’s Value Chain and Net Present Value. This is all fine so long as we remember:

  • The probability of Payoff is risky. Since the value is created in the future, we can’t be certain about it happening - we should never consider it a done-deal. Future Value is always at risk. In finance, for example, we account for this in our future cash-flows by discounting them according to the risk of default.
  • The Payoff amount is risky. Additionally, whereas in a financial transaction (like a loan, say), we might know the size of a future payment, in IT projects we can rarely be sure that they will deliver a certain return. On some fixed-contract projects this sometimes is not true: there may be a date when the payment-for-delivery gets made, but mostly we’ll be expecting an uncertain Payoff.
  • Humans tend to be optimists (especially when there are lots of Hidden Risks), hence our focus on Downside Risk. Sometimes though, it’s good to stand back and look at a scenario and think: am I capturing all the Upside Risk here?

Speed

Pillars, From Rapid Development By Steve McConnell

The diagram above reproduces a figure from Rapid Development by Steve McConnell. This is fine: McConnell is structuring the process from the perspective of delivering as quickly as possible. However, here, I want to turn this on its head. Software Development from a risk-first perspective is an under-explored technique, and I believe it offers some useful insights. So the aim here is to present the case for viewing software development like this:

Pillars, re-arranged

As we will see, Speed (or Schedule Risk as we will term it) is one risk amongst others that need to be considered from a risk-management perspective. There’s no point in prioritising speed if the software fails in production due to Operational Risk issues and damages trust in the product.

Eisenhower’s Box

A basic "Eisenhower box" to help evaluate urgency and importance. Items may be placed at more precise points within each quadrant.  - Adapted From [Time Management, _Wikipedia_](https://en.wikipedia.org/wiki/Time_management)

Eisenhower’s Box is a simple model allowing us to consider two aspects of risk at the same time:

  • How valuable the work is (Importance, Value).
  • How soon it is needed (Urgency, Time, Speed).

The problem is, we now need to choose whether to do something that is urgent or something that is important.

Discounting

We can use Net Present Value to discount value in the future, which offers us a way to reconcile these two variables. The further in the future the value is realised, the bigger the discount. This is done because payment now is better than payment in the future: there is the risk that something will happen to prevent that future payment. This is why we have interest rates on loan payments.

Net Present Value Discounting

In the diagram above, you can see two future payments: Payment A of £100 due in one year, and Payment B of £150 due in 10 years. By discounting at a given rate (here at a high rate of 20% per year) we can compare their worth now. At this discount rate, Payment A - arriving next year - has a far greater value.

Can we do the same thing with risk? Let’s introduce the concept of Net Present Risk, or NPR:

Net Present Risk is the Impact of a Future risk, discounted to a common level of Urgency.

Let’s look at a quick example to see how this could work out. Let’s say you had the following risks:

  • Risk A, which will cost you £50 in 5 days’ time.
  • Risk B, which will cost you £70 in 8 days’ time.

Net Present Risk, 6% Discount Rate

Which has the biggest NPR? Well, it depends on the discount rate that you apply. The graph above assumes we are discounting at 6% per day. On this basis, the biggest NPR is B, at about £45.

Net Present Risk, 20% Discount Rate

However, the graph above increases the discount factor to 20% and we get a different result: Now, risk A is bigger.

Because this is Net Present Risk, we can also use it to make decisions about whether or not to mitigate risks. Let’s assume the cost of mitigating any risk right now is £40. Under the 6% regime, only Risk B is worth mitigating today, because you spend £40 today to get rid of £45 of risk (today).

Under the 20% regime, neither are worth mitigating. The 20% Discount Rate may reflect that sometimes, future risks just don’t materialise.

Discounting the Future To Zero

I have worked in teams sometimes where the blinkers go down, and the only thing that matters is now. Anything with a horizon over a week is irrelevant. Regimes of such hyper-inflation are a sure sign that something has really broken down within a project. Consider in this case a Discount Factor of 60% per day, and the following risks:

  • Risk A, £10 cost, happening tomorrow
  • Risk B, £70 cost, happening in 5 days.

Risk B is almost irrelevant under this regime, as this graph shows:

Net Present Risk, 60% Discount Rate

Why do things like this happen? Often, the people involved are under incredible job-stress: usually they are threatened on a daily basis, and therefore feel they have to react. In a similar way, publicly-listed companies also often apply short-term focus, because they only care about the next annual report, which limits their horizons and ability to consider future risk.

Under these circumstances, we often see Pooh-Bear Procrastination:

“Here is Edward Bear coming downstairs now, bump, bump, bump, on the back of his head, behind Christopher Robin. It is, as far as he knows, the only way of coming downstairs, but sometimes he feels that there really is another way…if only he could stop bumping for a moment and think of it!” - A. A. Milne, Winne-the-Pooh

Is This Scientific?

Enough with the numbers and the theory: we need a practical framework, rather than a scientifically rigorous analysis. For software development, you should probably give up on trying to compute risk numerically. You can’t work out how long a software project will take based purely on an analysis of (say) function points. (Whatever you define them to be).

  • First, there isn’t enough scientific evidence for an approach like this. We can look at collected data about IT projects, but techniques and tools advance rapidly.
  • Second, IT projects have too many confounding factors, such as experience of the teams, technologies used etc. That is, the risks faced by IT projects are too diverse and hard to quantify to allow for meaningful comparison from one to the next.
  • Third, as soon as you publish a date it changes the expectations of the project (see Student Syndrome).
  • Fourth, metrics get misused and gamed (as we will see in a later chapter).

Reality is messy. Dressing it up with numbers doesn’t change that and you risk fooling yourself. If this is the case, is there any hope at all in what we’re doing? Yes: forget precision. You should, with experience, be able to hold up two separate risks and answer the question, “is this one bigger than this one?”

With that in mind, let’s look at how we can meet reality as fast and as often as possible.