Estimates

In this section, we’re going to put a Risk-First spin on the process of Estimating. But in order to get there, we first need to start with understanding why we estimate. We’re going to look at some “Old Saws” of software estimation and what we can learn from them. Finally, we’ll bring our Risk-First menagerie to bear on de-risking the estimation process.

The Purpose Of Estimating

Why bother estimating at all? There are two reasons why estimates are useful:

  1. To allow for the creation of events. As we saw in Deadline Risk, if we can put a date on something, we can mitigate lots of Coordination Risk. Having a release date for a product allows whole teams of people to coordinate their activities in ways that hugely reduce the need for Communication. “Attack at dawn” allows disparate army units to avoid the Coordination Risk inherent in “attack on my signal”. This is a good reason for estimating because by using events you are mitigating Coordination Risk. This is often called a hard deadline.

  2. To allow for the estimation of the Payoff of an action. This is a bad reason for estimating as we will discuss in detail below. But briefly the main issue is that Payoff isn’t just about figuring out Schedule Risk - you should be looking at all the other Attendant Risks of the action too.

How Estimates Fail

Estimates are a huge source of contention in the software world:

“Typically, effort estimates are over-optimistic and there is a strong over-confidence in their accuracy. The mean effort overrun seems to be about 30% and not decreasing over time.” - Software Development Effort Estimation, Wikipedia.

In their research “Anchoring and Adjustment in Software Estimation”, Aranda and Easterbrook asked developers split into three groups (A, B and Control) to give individual estimates on how long a piece of software would take to build. They were each given the same specification. However:

How long would members of each group estimate the work to take? The results were startling. On average,

The anchor mattered more than experience, how formal the estimation method, or anything else. We can’t estimate time at all.

Is Risk To Blame?

Estimates:  Attendant Risks

Why is it so bad? The problem with a developer answering a question such as:

“How long will it take to deliver X?”

Seems to be the following:

… and so on. This is summarised in the above diagram. It’s no wonder people hate estimating: the treatment is worse than the disease.

So what are we to do? It’s a problem as old as software itself, and in deference to that, let’s examine the estimating problem via some “Old Saws”.

Old Saw No. 1: The “10X Developer”

“A 10X developer is an individual who is thought to be as productive as 10 others in his or her field. The 10X developer would produce 10 times the outcomes of other colleagues, in a production, engineering or software design environment.” - 10X Developer, Techopedia

Let’s try and pull this apart:

1X Task vs 10X Task

Does the “10X Developer” even exist? Crucially, it would seem that such a thing would be predicated on the existence of the “1X Developer”, who gets “1X” worth of work done each day. It’s not clear that there is any such thing as an average developer who is mitigating risk at an average rate.

Even good developers have bad days, weeks or projects. Taking Action is like placing a bet. Sometimes you lose and the Payoff doesn’t appear:

The easiest way to be the “10X developer” is to have done the job before. If you’re coding in a familiar language, with familiar libraries and tools, delivering a cookie-cutter solution to a problem in the same manner you’ve done several times before, then you will be a “10X Developer” compared to you doing it the first time because:

Old Saw No. 2: Quality, Speed, Cost: Pick Any Two

Brooks' Law, Risk-First Style

“The Project Management Triangle (called also the Triple Constraint, Iron Triangle and Project Triangle) is a model of the constraints of project management. While its origins are unclear, it has been used since at least the 1950s. It contends that:

  1. The quality of work is constrained by the project’s budget, deadlines and scope (features).
  2. The project manager can trade between constraints.
  3. Changes in one constraint necessitate changes in others to compensate or quality will suffer.”

From a Risk-First perspective, we can now see that this is an over-simplification. If quality is a Feature Fit metric, deadlines is Schedule Risk and budget refers to Funding Risk then that leaves us with a lot of risks unaccounted for:

“Brooks’ law is an observation about software project management according to which ‘adding human resources to a late software project makes it later’. - Brooks Law, Wikipedia

So the conclusion is: Focusing on the three risks of the iron triangle isn’t enough. You can game these risks by sacrificing others: we need to be looking at the project’s risk holistically.

Old Saw No. 3: Parkinson’s Law

“Parkinson’s law is the adage that ‘work expands so as to fill the time available for its completion’.” - Parkinson’s Law, Wikipedia

Let’s leave aside the Devil Makes Work-style Agency Risk concerns this time. Instead, let’s consider this from a Risk-First perspective. Of course work would expand to fill the time available: Time available is an absence of Schedule Risk. It’s always going to be sensible to exchange free time to reduce more serious risks.

This is why projects will always take at least as long as is budgeted for them.

A Case Study

Let’s look at a quick example of this in action, taken from Rapid Development by Steve McConnell. At the point of this excerpt, Carl (the Project Manager) is discussing the schedule with Bill, the project sponsor:

“I think it will take about 9 months, but that’s just a rough estimate at this point,” Carl said. “That’s not going to work,” Bill said. “I was hoping you’d say 3 or 4 months. We absolutely need to bring that system in within 6 months. Can you do it in 6?” (1)

Later in the story, the schedule has slipped twice and is about to slip again:

… at the 9-month mark, the team had completed detailed design, but coding still hadn’t begun on some modules. It was clear that Carl couldn’t make the 10-month schedule either. He announced the third schedule slip to 12 months. Bill’s face turned red when Carl announced the slip, and the pressure from him became more intense. (2)

Carl's Schedule Slip increases Trust and Belief Risks

At point (2), Carl has tried to mitigate Feature Risk by increasing Schedule Risk, although he knows that Bill will trust him less for doing this, as shown in the diagram above. Let’s continue…

Carl began to feel that his job was on the line. Coding proceeded fairly well, but a few areas needed redesign and reimplementation. The team hadn’t coordinated design details in those areas well, and some of their implementations conflicted. At the 11-month oversight-committee meeting, Carl announced the fourth schedule slip— to 13 months. Bill became livid. “Do you have any idea what you’re doing?” he yelled. “You obviously don’t have any idea! You obviously don’t have any idea when the project is going to be done! I’ll tell you when it’s going to be done! It’s going to be done by the 13-month mark, or you’re going to be out of a job! I’m tired of being jerked around by you software guys! You and your team are going to work 60 hours a week until you deliver!” (3)

At point (3) in McConnell’s Case Study, the schedule has slipped again and Bill has threatened Carl’s job. Why did he do this? Because he doesn’t trust Carl’s evaluation of the Schedule Risk. By telling Carl that it’s his job on the line he makes sure Carl appreciates the Schedule Risk.

Bill's Ultimatum

However, forcing staff to do overtime is a dangerous ploy: it could disenfranchise the staff, or cause corners to be cut, as shown in the diagram above.

Carl felt his blood pressure rise, especially since Bill had backed him into an unrealistic schedule in the first place. But he knew that with four schedule slips under his belt, he had no credibility left. He felt that he had to knuckle under to the mandatory overtime or he would lose his job. Carl told his team about the meeting. They worked hard and managed to deliver the software in just over 13 months. Additional implementation uncovered additional design flaws, but with everyone working 60 hours a week, they delivered the product through sweat and sheer willpower. “ (4) - McConnell, Steve, Rapid Development

At point (4), we see that Bill’s gamble worked (for him at least): the project was delivered by the team working overtime for two months. This was lucky - it seems unlikely that no-one quit and that the code didn’t descend into a mess in that time.

Team Response

The diagram above shows the action taken, working overtime. Despite this being a fictional (or fictionalised) example, it rings true for many projects. What should have happened at point (1)? Both Carl and Bill estimated incorrectly… Or did they? Was this just Parkinson’s Law in operation?

Agile Estimation

One alternative approach, much espoused in DevOps/Agile is to pick a short-enough period of time (say, two days or two weeks) and figure out what the most meaningful step towards achieving an objective would be in that time. By fixing the time period, we remove Schedule Risk from the equation, don’t we?

Well, no. First, how to choose the time period? Schedule Risk tends to creep back in, in the form of something like Person-Hours or Story Points:

“Story points rate the relative effort of work in a Fibonacci-like format: 0, 0.5, 1, 2, 3, 5, 8, 13, 20, 40, 100. It may sound counter-intuitive, but that abstraction is actually helpful because it pushes the team to make tougher decisions around the difficulty of work. “ - Story Points, Atlassian

Second, the strategy of picking the two-day action with the greatest Payoff is often good. (After all, this is just Gradient Descent and that’s a perfectly good way for training Machine Learning systems.) However, just like following a river downhill from the top of a mountain will often get you to the sea, it probably won’t take the shortest path and sometimes you’ll get stuck at a lake.

The choice of using gradient descent means that you have given up on Goals: essentially, we have here the difference between “Walking towards a destination” and “Walking downhill”. Or, if you like, a planned economy and a market economy. But, we don’t live in either: everyone lives in some mixture of the two: our governments have plans for big things like roads and hospitals, and taxes. Other stuff, they leave to the whims of supply and demand. A project ends up being the same.

Risk-First Estimating

Let’s figure out what we can take away from the above experiences:

How can we synthesise this knowledge, along with what we’ve learned into something that makes more sense?

Tip #1: Estimating Should be About Estimating Payoff

For a given action / road-map / business strategy, what Attendant Risks are we going to have?

Instead of the Agile Estimation being about picking out a story-point number based on some idealised amount of work that needs to be done, it should be about surfacing and weighing up risks. e.g:

Risk-First Diagram Language

Essentially, this is what we are trying to capture with Risk-First Diagrams (the diagram above being the template for this).

Tip #2: The Risk Landscape is Increasingly Complex: Utilise This

Journey via the Central Line

If you were travelling across London from Ealing (in the West) to Stratford (in the East) the fastest route might be to take the Central Line. You could do it via the A406 road, which would take a bit longer. It would feel like you’re mainly going in completely the wrong direction doing that, but it’s much faster than cutting straight through London and you don’t pay the congestion charge.

Journey by Car

In terms of risk, they all have different profiles. You’re often delayed in the car, by some amount. The tube is generally reliable, but when it breaks down or is being repaired it might end up quicker to walk.

If you were doing this same journey on foot, it’s a very direct route, but would take five times longer. However, if you were making this journey a hundred years ago that might be the only choice (horseback might be a bit faster).

Journey on Foot

In the software development past, building it yourself was the only way to get anything done. It was like London before road and rail. Nowadays, you are bombarded with choices. It’s actually worse than London because it’s not even a two-dimensional geographic space and there are multitudes of different routes and acceptable destinations. Journey planning on the software Risk Landscape is an optimisation problem par excellence.

Possible Moves On The Risk Landscape

Because the modern Risk Landscape is so complex:

Tip #3: Meet Reality Early on the Biggest Risks

In getting from A to B on the Risk Landscape imagine that all the Attendant Risks are the stages of a journey. Some might be on foot, train, car and so on. In order for your course of action to work all the stages in the journey have to succeed.

Although you might have to make the steps of a journey in some order, you can still mitigate risk in a different order. For example, checking the trains are running, making sure your bike is working, booking tickets and taxis, and so on.

The sensible approach would be to test the steps in order from weakest to strongest. This means working out how to meet reality for each risk in turn, in order from biggest risk to smallest.

Often, a strategy will be broken up into multiple actions. Which are the riskiest actions? Figure this out, using the Risk-First vocabulary and the best experience you can bring to bear, then, perform the actions which Payoff the biggest risks first.

As we saw from the “10X Developer” Saw, Learning Curve Risk and Dead End Risk, are likely to be the biggest risks. How can we front-load this and tackle these earlier?

Tip #4: Talk Frankly About All The Risks

Let’s get back to Bill and Carl. What went wrong between points (1) and (2)? Let’s break it down:

“I think it will take about 9 months, but that’s just a rough estimate at this point,” Carl said. “That’s not going to work,” Bill said. “I was hoping you’d say 3 or 4 months. I need to show the board something by then or I’m worried they will lose confidence in me and this project”.

“OK,” said Carl. “But I’m really concerned we have huge Feature Fit Risk. The task of understanding the requirements and doing the design is massive.”

“Well, in my head it’s actually pretty simple, “ said Bill. “Maybe I don’t have the full picture, or maybe your idea of what to build is more complex than I think it needs to be. That’s a massive risk right there and I think we should try and mitigate it right now before things progress. Maybe I’ll need to go back to the board if it’s worse than I think. “

Identifying The Action

Tip #5: Picture Worrying Futures

The Bill/Carl problem is somewhat trivial (not to mention likely fictional). How about one from real life? On a project I was working on in November some years ago, we had two pieces of functionality we needed: “Bulk Uploads” and “Spock Integration”. (It doesn’t really matter what these are). The bulk uploads would be useful now. But, the Spock Integration wasn’t due until January. In the Spock estimation meeting I wrote the following note:

“Spock estimates were 4, 11 and 22 until we broke it down into tasks. Now, estimates are above 55 for the whole piece. And worryingly, we probably don’t have all the tasks. We know we need bulk uploads in November. Spock is January. So, do bulk uploads? “

The team wanted to start Bulk Uploads work. After all, from these estimates it looked like Spock could easily be completed in January. However, the question should have been:

“If it was February now, and we’d got nothing done, what would our biggest risk be?”

Missing Bulk Uploads wouldn’t be a show-stopper, but missing Spock would be a huge regulatory problem. Start work on the things you can’t miss.

In Summary…

Let’s recap those again, in reverse order: